Posts Tagged ‘egan’

Summer of School Upgrades and Installs

Friday, September 19th, 2014

anoka-hennepin-school-outsideEvery summer, Egan Company’s Building Systems & Services (BSS) group upgrades or installs new building automation or fire systems in schools across Minnesota and Wisconsin.

Egan completed work this summer in over eight school districts, including St. Paul Public Schools, Eden Prairie Schools, Anoka-Hennepin School District, School District of Clear Lake, and St. Michael-Albertville School District. All of this work is compressed into a three-month timeframe and equates to over 20,000 hours of manpower.

The building automation system controls everything from air handling units to VAV boxes to pool converters to lighting. Many schools also incorporate energy efficient systems to produce lower utility bills. The fire systems in the schools provide smoke management systems, advance detection, voice evacuation and exit technology, and sprinkler system monitoring.

The installation of these two systems can prove challenging, especially in such a short timeframe; however, Egan simplifies the project process by providing system engineering, design, installation, and start-up and commissioning to finish the job quickly.

All systems were updated before school started this Fall. Year round, Egan also provides maintenance to these–and other–school districts.

“Every summer we roll up our sleeves for various schools,” said Tom Addabbo, Egan Account Manager. “It’s always a challenge to help bring these schools back online before the school year starts. Fortunately, our field team does it year after year and knows what it takes to meet these tight timelines.”

Summer 2014 Numbers At-a-Glance

  • 4,505 hours of building automation system setup, engineering, graphics, and drafting
  • 11,290 hours of building automation field installs
  • 1,681 hours of building automation commissioning
  • 4,900 hours of fire systems field installs
  • 538 hours of fire systems testing and inspection

Technology bands Egan Together

Wednesday, September 17th, 2014

jim-nonnJim Nonn, Egan Company’s Chief Information Officer hadn’t planned for this. As he watched the antenna wave in the -20 degree wind chill, he thought, “This isn’t going to work.”

The antenna was part of a new “air-fiber” connection that sends/receives data from Egan’s corporate headquarters to Egan’s Industrial Controls group about a mile away at speeds of 1.4 Gigabytes/second. The connection consisted of two antennae on top of each building that needed direct, uninterrupted line-of-sight to each other.

Minnesota’s December weather had other plans. Not only was the antenna failing to stay put in the freezing wind, but it was also too short. Line-of-sight to Industrial Controls was cut off by another building. If these antennae failed to work, the Industrial Controls employees may as well have not shown up to work next Monday.

With the help of Egan pipefitters and low-voltage electrical employees, a team was formed to find a solution.

A taller, sturdier tower was fabricated in Egan’s pipe shop, customized electrical wiring was rigged to it, and a bucket truck and crane were procured to safely install the new equipment. All of this was completed same-day.

“It’s one of those times when I’m really glad I work at Egan, not just because of our construction capabilities, but the fact that people are willing to drop everything and help when you need it most,” Nonn said.

Both antennae have needed minimal maintenance since that icy December day, and connection speeds between Egan locations have been consistently superior.

Collaboration with millwrights for safety, precision, and speed

Monday, September 15th, 2014

On a Tuesday afternoon, Egan Company was tasked with a project: Daktronics, a scoreboard and electronic display company, needed help to safely raise 3,000 pounds of cable dangling 150 feet from the Xcel Energy Center ceiling. And it had to be done in 72 hours.

The scoreboard had been lowered, taken apart, and left in the middle of the Xcel with wires dangling from the ceiling. In three days, the Xcel needed to be set up for a Rod Stewart concert. Xcel thought the wires could be raised and set on the catwalks high above the floor; however, the catwalks could not support the weight of the cables.

Further situation analysis by Egan’s Electrical Foreman, Project Manager, and Safety Director led to a concern with safety.

They concluded that a millwright needed to be involved to ensure the cables were lifted and installed safely. Egan Certified Millwright Marc Beltz met the team at the Xcel to determine a safe solution.

Egan’s millwright team is safe, efficient, and thorough. They understand what is needed to make the project work and that the needs of the client are to be met.

–Jason Hanlon, Braun Intertec Associate Principal/Senior Structural Engineer

Since 1999, Egan Company has offered millwright services to customers. Millwrights specialize in safely moving heavy equipment and the precise alignment of machines. Essentially, a millwright is an industrial mechanic.

Beltz and the electrical team partnered with Braun Intertec to develop a plan to raise the cables. Braun Intertec engineered rigging that met Egan’s objective to safely lift the heavy cables. The design was completed by early afternoon on Wednesday and the steel rig was fabricated on site by the Egan millwright team the next day.
millwright3

Egan’s millwright team understands that all procedures, design, and construction need to meet certain standards and requirements before the work can be completed,

said Jason Hanlon, Associate Principal/Senior Structural Engineer at Braun Intertec.

It takes more than just muscle to complete a job like this. Egan millwrights work with a high degree of precision and certainty to ensure proper installation of heavy materials. Once a precise and safe installation procedure was established on Thursday, the cables was lifted and installed in the ceiling in time for fans to enjoy the Rod Stewart concert.
Beltz attributes the success of this job to the great collaboration between groups at Egan.

We have the opportunity to work with every group at Egan and also collaborate with engineering firms,

Beltz said. “We’re proud to offer millwright services to customers.”

Beyond precisely moving heavy equipment, Egan millwright services also include welding, machinery installation, rigging, preventative maintenance for mechanical equipment, optical and laser alignment, and custom fabrication.
Primarily, Egan millwrights work in the power plant, foundry, food production, and manufacturing industries.

“We provide specialized services that you can’t get from anyone else but a millwright,” Beltz said. “If it moves, you need a millwright.”

Historically, the “mill” in millwright comes from building and maintaining flour mills, paper mills, and sawmills powered by wind and water. Though the trade has evolved since then, the basic idea is the same: to provide customers with necessary services to keep industries producing.