Summer of School Upgrades and Installs

September 19, 2014

anoka-hennepin-school-outsideEvery summer, Egan Company’s Building Systems & Services (BSS) group upgrades or installs new building automation or fire systems in schools across Minnesota and Wisconsin.

Egan completed work this summer in over eight school districts, including St. Paul Public Schools, Eden Prairie Schools, Anoka-Hennepin School District, School District of Clear Lake, and St. Michael-Albertville School District. All of this work is compressed into a three-month timeframe and equates to over 20,000 hours of manpower.

The building automation system controls everything from air handling units to VAV boxes to pool converters to lighting. Many schools also incorporate energy efficient systems to produce lower utility bills. The fire systems in the schools provide smoke management systems, advance detection, voice evacuation and exit technology, and sprinkler system monitoring.

The installation of these two systems can prove challenging, especially in such a short timeframe; however, Egan simplifies the project process by providing system engineering, design, installation, and start-up and commissioning to finish the job quickly.

All systems were updated before school started this Fall. Year round, Egan also provides maintenance to these–and other–school districts.

“Every summer we roll up our sleeves for various schools,” said Tom Addabbo, Egan Account Manager. “It’s always a challenge to help bring these schools back online before the school year starts. Fortunately, our field team does it year after year and knows what it takes to meet these tight timelines.”

Summer 2014 Numbers At-a-Glance

  • 4,505 hours of building automation system setup, engineering, graphics, and drafting
  • 11,290 hours of building automation field installs
  • 1,681 hours of building automation commissioning
  • 4,900 hours of fire systems field installs
  • 538 hours of fire systems testing and inspection