Louise Solar
SUPER SOLAR EXCITEMENT
PROJECT:
Louise Solar
LOCATION:
Adams, Minnesota
BUILDING TYPE:
Renewable Energy
EGAN EXPERTISE:
Solar
PROJECT TEAM:
National Grid Renewables
Berry Construction
Westwood
PROJECT FACTS:
In total, the solar field can generate up to 65.9 megawatts of energy at peak production.
SPECIALTIES FEATURED WITH THIS PROJECT:
Electrical Construction
- Spanning approximately 600 acres, the Louise Solar Project in Adams, Minn. is one of the largest solar fields Egan Company has worked on to date.
- The solar panels are divided among three sites to maximize land usage.
- Egan’s Electrical Construction team installed (14) 4400kVA inverters, (259) 1500VDC combiners, 142,332 first solar series 6 modules, and over 240,000 feet of direct bury cable for the single-axis tracking system.
- The project was completed in 10 months, finishing in September 2024.