PROJECT:

Second Harvest Heartland

LOCATION:

Brooklyn Park, Minn.

BUILDING TYPE:

Office Building / Industrial & Manufacturing

EGAN EXPERTISE:

HVAC installation

PROJECT TEAM:

PCL Construction
AECOM
LEO A DALY

PROJECT FACTS:

Phase I of this project was completed in September 2019. // Phase II was completed in February 2020. //

SPECIALTIES FEATURED WITH THIS PROJECT:

Mechanical

  • Second Harvest Heartland is one of the nation’s largest food banks. After spending 30 years operating in Maplewood, the nonprofit organization recently moved its headquarters to Brooklyn Park, Minn.
  • The newly reconstructed space includes more capacity for volunteers, fresh food storage, distribution, as well as corporate offices.
  • Egan’s mechanical team was tasked with two phases on this reconstruction project. The scope of work included all HVAC throughout the 150,000 square foot space.
  • Equipment installed included:
    -Two (2) Energy Recovery units that feed tempered outside air to the Variable Refrigerant Flow (VRF) System
    -Two (2) Makeup Air units for pressure control within the warehouse
    -A rooftop unit for the food packing space within the new volunteer area
    -Outside air, return air, exhaust air, and supply air systems for the VRF fan coils
    -Five (5) high-volume, low-speed ceiling fans
    -Five (5) unit heaters with electric coils
  • Egan pipefitters installed gas piping to all gas-fired makeup units, rooftop units, and energy recovery systems.